AACE Recommended Practice 98R-18 is the cost estimate classification system specifically developed for the road and rail transportation infrastructure industries. Of all the AACE recommended practices, this is the most directly relevant to PCEM users.
Published in 2018 and revised in 2020, RP 98R-18 supplements the generic classification RP (17R-97) by providing a project definition deliverable maturity matrix specifically for road and rail projects. It maps design deliverables such as alignment studies, geotechnical investigations, environmental assessments, and detailed drawings against estimate class, providing a structured way to assess estimate maturity based on actual project deliverables.
How RP 98R-18 Compares to PCEM Phase Requirements
| RP 98R-18 Class |
Key Design Deliverables |
Closest PCEM Phase |
PCEM Deliverable Equivalent |
| Class 5 |
Route selection studies, preliminary environmental scoping |
Strategic Planning |
TIPPS submissions, strategic options assessment |
| Class 4 |
Feasibility studies, preliminary alignment, initial geotechnical |
Concept (SASR / Options) |
SASR estimate, options analysis |
| Class 3 |
Preliminary design, detailed geotechnical, traffic modelling |
Concept (Business Case) / Development (S1D) |
Business case estimate, S1D budget verification |
| Class 2 |
Detailed design, final environmental approvals, construction plans |
Development (S2D) |
S2D pre-tender estimate, EFCT |
| Class 1 |
IFC drawings, complete specifications, tender documentation |
Development (APDV) / Implementation |
APDV, contract award, cost forecasts |
The alignment between RP 98R-18 and PCEM is notably strong because both frameworks were developed for the same industry sector: road and rail infrastructure. The design deliverables that RP 98R-18 uses to determine estimate class are essentially the same deliverables that PCEM requires at each phase gate. This makes cross-referencing between the two frameworks straightforward in practice.
Practical Tip
When preparing estimates for Queensland projects that also require federal reporting, use the RP 98R-18 deliverable maturity matrix as a checklist alongside PCEM requirements. If your estimate satisfies the PCEM phase gate requirements, it will typically also satisfy the equivalent RP 98R-18 class requirements, giving you confidence in dual-framework compliance.