AACE Estimate Classification: Check Estimate or Bid/Tender

AACE Class 1 Estimate

The most detailed estimate in the system. A Class 1 estimate is usually prepared for critical parts of a project to check a bid, price a change or resolve a claim.

Updated 2 October 2026

At a Glance

Class 1 Estimate Characteristics

The five attributes AACE uses to describe each class. Project definition maturity is the one that decides the class; the others follow from it.

Project definition65% to 100% of full definition
Typical end usageCheck estimates, bid validation, change orders, claims and disputes
Estimating method (general, RP 18R-97)Detailed unit costs with detailed take-off
Estimating method (road and rail, RP 98R-18)Unit-rate line items on actual design quantities, usually for critical parts of the project
Expected accuracy (80% confidence)Low: −3% to −10%
High: +3% to +15%
Other namesDefinitive, check estimate, fair price, firm price, bottom-up, change order estimate
Typical stageExecution; Queensland PCEM: Implementation (pre-award validation)
Overview

What a Class 1 Estimate Is

A Class 1 estimate is prepared when 65% to 100% of the project is defined, with some owners calling for a 90% design review. Virtually all design documentation exists, along with complete execution and commissioning plans.

The expected accuracy is -3% to -10% on the low side and +3% to +15% on the high side. Even at full design, the range is not zero: productivity, market conditions and site conditions still vary.

Because the effort is high, Class 1 estimates are rarely prepared for an entire project. They are targeted at the packages where precision matters most: a large subcontract, a disputed variation, or a tender that looks too low.

What needs to be defined

Typical status of key deliverables for a road or rail project at Class 1. The class follows the weakest deliverable that materially affects cost, not the average.

  • All or nearly all design deliverables complete (issued for construction)
  • Complete specifications and tender documentation
  • Execution, staging and commissioning plans complete
  • Long-lead items in fabrication or on order

How it is prepared

Every item is a unit-rate line priced on actual design quantities, with rates built up from labour, plant, materials and subcontract prices. The estimator works at the level a contractor would plan the work.

This is the class used to check whether a tender price is fair, to evaluate variations, and to support claims and dispute resolution, where the estimate may be tested line by line.

Worked Example

What the Class 1 Range Means in Dollars

Illustrative figures for an independent check estimate for a bridge package before contract award: an estimate of $12M including contingency.

Project risk profileAccuracy range80% confidence range of final cost
Well understood, low risk (tight end of the band)−3% / +3%$11.64M to $12.36M
Complex or high risk (wide end of the band)−10% / +15%$10.8M to $13.8M

Try it with your own estimate

The accuracy range calculator applies the published bands for every class to your figure, and shows where your project might sit within them.

Open the calculator

AACE stresses that these bands are typical outcomes, not targets. The range for a particular estimate should come from a quantitative risk analysis. See P50 and P90 explained.

Avoid These

Common Class 1 Mistakes

  • Preparing a 'definitive' estimate for the whole project when only critical packages justify the effort
  • Assuming design is complete when some packages are still at Class 2 maturity
  • Comparing a Class 1 check estimate with a tender on a different scope or risk allocation
  • Treating a Class 1 range as guaranteed: unusual site or market conditions can still push outcomes outside it

In Queensland, a Class 1 estimate broadly corresponds to the PCEM Implementation (pre-award validation) phase. The mapping is approximate; see AACE vs PCEM for how the two frameworks line up.

FAQ

Frequently Asked Questions

What is an AACE Class 1 estimate?

A Class 1 estimate is the most defined class in the AACE system, prepared with 65% to 100% of project definition using detailed unit costs and detailed take-off. Its expected accuracy is -3% to -10% on the low side and +3% to +15% on the high side at 80% confidence.

Is a Class 1 estimate the same as a definitive estimate?

Definitive, check, fair price and firm price estimates are all common names for Class 1. The class ties the name to a defined level of project maturity.

When is a Class 1 estimate used?

Mainly for check estimates before contract award, for bid validation, and for pricing changes, claims and disputes. It is usually prepared for critical packages rather than the whole project.