15% below your estimate
AACE Estimate Accuracy Range Calculator
Enter an estimate, choose its class, and see the range the final cost is likely to fall within, using the accuracy bands AACE International publishes for each class.
Updated 2 October 2026
Class 3 · 80% confidence
Including contingency
20% above your estimate
There is roughly an 80% chance the final cost lands between $21.3M and $30M.
- Full published range for the class
- Where your project sits
- Your estimate
Show the numbers for every class
| Class | Low | High | 80% confidence range |
|---|
Which Class Is My Estimate?
Answer four questions about what exists today. AACE classes an estimate by the maturity of its deliverables, and the least mature deliverable that materially affects cost decides the class.
AACE Accuracy Ranges by Class
Typical variation in the low and high ranges at an 80% confidence interval, from RP 18R-97 (process industries) and RP 98R-18 (road and rail), which publish identical bands.
How to Use These Ranges Properly
- The class comes from the deliverables, not the dollar figure. Decide the class from the maturity of the design, survey, geotechnical and other key deliverables. If they are uneven, use the weakest one that materially affects cost.
- The ranges assume contingency is already included. Apply them to the estimate with contingency, not to the base estimate.
- They are typical outcomes, not targets. AACE expects the range for a specific estimate to come from a quantitative risk analysis, such as Monte Carlo simulation, which also gives the P50 and P90 values funders ask for.
- Unusual risks widen the range. Volatile markets, political or stakeholder uncertainty and difficult ground can push outcomes beyond the published bands.
Related: the estimate classification system, P50 and P90 explained, and the Monte Carlo method.
Frequently Asked Questions
How do I calculate the accuracy range of an AACE estimate?
Multiply the estimate (including contingency) by one plus the low and high percentages for its class. For a Class 3 estimate of $25 million at the wide end of the band (-20% / +30%), the 80% confidence range is $20 million to $32.5 million. AACE recommends deriving the actual range for a specific estimate from a quantitative risk analysis.
Why are AACE accuracy ranges asymmetric?
Because capital projects are far more likely to overrun than underrun. The high side of every band is larger than the low side, and the difference grows as project definition falls.
Do the accuracy ranges include contingency?
Yes. The published ranges assume the estimate already includes an appropriate contingency. Without contingency the range would be wider and shifted upward.
Are the ranges different for road and rail projects?
No. RP 98R-18 for road and rail publishes the same accuracy bands as RP 18R-97 for the process industries. What differs is how each class is prepared, for example cost per kilometre at Class 5 and Class 4.