TMR · RES · DITRDCA

Australian Cost-Risk & Contingency Frameworks Compared

Queensland's TMR mandate, the national RES best-practice guideline and the Commonwealth's DITRDCA funding guidance were written by different bodies for different purposes — yet they prescribe the same discipline. Three frameworks, one method.

The one-line story

Three Frameworks, One Method

The TMR Project Risk Management & Contingency Development Process Manual (1st Ed, March 2023), the RES Contingency Guideline (3rd Ed, 2025) and the Commonwealth's DITRDCA Cost Estimation Guidance (Guidance Notes, v2.0, Nov 2023) read like three separate rulebooks. In substance they prescribe the same discipline:

A first-principles base estimate; risk modelled probabilistically with Monte Carlo simulation; contingency reported at P50 and P90; escalation kept separate; and flat-percentage contingency discouraged. A firm that genuinely speaks all three doesn't switch methods per client — it applies one rigorous method and reports it in each framework's language.

TMR Queensland · mandatory RES National · best practice DITRDCA Commonwealth · mandatory ONE SHARED METHOD First-principles base estimate + Monte Carlo contingency REPORTED AT P50 / P90
The three core frameworks

Side by Side, Dimension by Dimension

Fourteen dimensions across the three frameworks a Queensland or federally funded project is most likely to be assessed against. The differences are in vocabulary and emphasis — the underlying discipline is shared.

Dimension TMR (Queensland) RES (national best practice) DITRDCA (Commonwealth)
Full title Project Risk Management & Contingency Development Process Manual, 1st Ed (Mar 2023) RES Contingency Guideline, 3rd Ed (2025) Cost Estimation Guidance (Guidance Notes, v2.0 Nov 2023)
Status Mandatory for QTRIP / state-funded transport projects Guidance, not a mandatory standard Mandatory for Infrastructure Investment Program funding
Estimate structure Base + contingency + escalation Base + contingency + Management Reserve (escalation out of scope) Base + contingency + escalation
Base method First-principles First-principles assumed First-principles preferred (client + construction costs; PLMS build-ups)
Probabilistic trigger State > $10M; federal > $25M Simulation recommended > $10M Out-turn incl. contingency > $25M
Preferred QRA method Monte Carlo (@RISK named); inherent risk on line items + discrete contingent risks Monte Carlo / FPRA; bare 3-point cautioned at FID Monte Carlo; risk-factor method preferred (line-item ranging cautioned against)
Iterations ~10,000 (rule of thumb) — (method-dependent) 5,000–10,000 recommended
Distributions Uniform, Triangular, PERT, Discrete Triangular, BetaPert (prefers "Alt" forms), Lognormal Beta PERT, Triangular, Trigen
Correlation Must be modelled Strong emphasis (functional + applied) Must be defined ("cardinal rule")
Confidence levels P50 budget · P90 mandated beyond business case · P75 APDV at tender award P50 → PMB, P90 → Management Reserve (per org risk appetite); report P10/P50/P90 P50 = approval basis · P90 notionally held, released on demonstrated need
Flat-% deterministic "Not recommended"; < $25M only Not recommended (early/small only) "Simplistic… not recommended"
Optimism bias / RCF Cites Flyvbjerg in the project-delay category RCF = benchmark/governance check, not a method "Reference Class" dropdown in the PCB template
Reporting outputs S-curve, histogram, tornado, P5–P95 at 5% intervals, re-runnable @RISK files S-curve at P10/P50/P90; FPRA report S-curve / CDF, histogram, tornado, P50/P90
Escalation In PCEM; → P90 out-turn Excluded from the guideline's scope Note 4: RCOCI (road) / Rail-COCI (rail), zero-floor; → out-turn
Distinctive device APDV at P75 + portfolio drawdown / savings Management Reserve outside the PMB; Contingency X-Factor PCB template (auto-escalation); held-P90 funding

Reading the table

Where one framework names a tool (TMR's APDV, RES's Management Reserve, DITRDCA's PCB template) the other two have a functional equivalent. The estimate that satisfies one — bottom-up base, modelled correlation, Monte Carlo S-curve, P50/P90 — is structurally the estimate that satisfies all three.

The thresholds reconciled

$10M and $25M Point the Same Way

The triggers look like they conflict. They don't — each one says "model it probabilistically", just at a different cost band and funding source.

PROBABILISTIC MONTE CARLO REQUIRED DETERMINISTIC OK $0 $10M TMR state trigger $25M Commonwealth + TMR federal trigger (out-turn incl. contingency) Out-turn cost →

> $10M — TMR requires probabilistic modelling for state-funded projects; RES recommends simulation above this value too.

> $25M — both the Commonwealth (DITRDCA) and TMR (for federally funded work) require Monte Carlo for total out-turn cost including contingency above this figure.

Whether your project crosses TMR's $10M state trigger or the Commonwealth's $25M out-turn trigger, the answer is the same — model it probabilistically. Cenex builds the estimate to satisfy both.

From RES Appendix G

Every Australian Jurisdiction Is Converging

RES's Appendix G compiles each jurisdiction's own requirement. The pattern is unmistakable — probabilistic, P-value-based estimation is now the norm nationwide.

Jurisdiction Confidence levels Threshold / trigger Mandated method
Commonwealth — DITRDCA (IIP) Out-turn P50 / P90 Probabilistic > $25M out-turn Monte Carlo; PCB template
Commonwealth — Dept of Finance P50 (Stage 1) / P80 (Stage 2) Two-Stage Capital Works Monte Carlo S-curve
QLD — TMR P50 & P90 (P75 at award) Probabilistic > $25M (fed) / > $10M (state) Monte Carlo / risk workshop
NSW — INSW / TfNSW P50 & P90 Contingency ID > $100M Monte Carlo (min. for High-Profile / High-Risk)
VIC — DTF / OPV P90 approval; P60 at contract award HVHR framework Probabilistic, staged release
WA — Treasury SAMF P90 or P50 (HVHR) High-value / high-risk Probabilistic (buildings use layered %)
SA — TI17 / DIT EST600 P50 & P90 Full compliance ≥ $11M Probabilistic risk methods
TAS — SIIRP Not specified Documented in business case
NT None identified
ACT — Capital Framework Tier-based Tier 1 stochastic (Monte Carlo)

Takeaway: seven of eight states and territories, plus both Commonwealth pathways, now expect probabilistic, P-value contingency. The method Cenex uses is the method the country has standardised on.

Speak all three

Shared Glossary

The core terms mean the same thing in every framework. Framework-specific terms are defined on each framework's own page.

Base estimate — the expected cost of the defined scope, excluding contingency and escalation.

Contingency — the provision above the base estimate for residual (inherent + contingent) risk, sized to a chosen confidence level; expected to be expended.

Inherent risk — variability in items already measured in the base estimate (quantities, rates).

Contingent risk — discrete risk events not in the base estimate (probability × impact).

Escalation — cost growth over time (inflation / market); converts real cost to out-turn (nominal) cost; kept separate from contingency.

Out-turn cost — base + contingency + escalation; the nominal total.

P50 / P90 — cost with a 50% / 90% probability of not being exceeded (read off the S-curve).

Monte Carlo simulation — sampling the modelled distributions over thousands of iterations to produce the cost probability distribution (S-curve).

Framework-specific terms

Defined on the relevant page only: APDV, EFCT, RCP (TMR); PMB, Management Reserve, FPRA, QSRA, iQSCRA, Contingency X-Factor (RES); PCB, RCOCI, Rail-COCI, NoA (DITRDCA).

One evidence pack

What Cenex Delivers

Every one of these frameworks expects the same evidence pack. Cenex produces it as standard — and reports it in whichever framework's language your project is funded under.

  • First-principles base estimate (PLMS build-ups; direct / indirect / margin; auditable to a 4-level WBS).
  • Facilitated risk workshop and a dollarised risk register.
  • Monte Carlo model (@RISK, 5,000–10,000 iterations) with inherent risk on line items, discrete contingent risks, and correlation modelled.
  • S-curve, histogram and tornado outputs; contingency reported at P50 and P90 (plus P75 for TMR award / P60 for VIC award where relevant).
  • Escalation to out-turn cost handled separately (framework-appropriate indices).
  • Reference class forecasting as an independent benchmark cross-check on the modelled result.
  • Chartered-Engineer sign-off, with re-runnable native model files for the funder's review.

Most estimators can produce a contingency number. Far fewer can produce one that satisfies the specific framework a project is funded under, defend it against an independent Commonwealth or TMR review, and report it in P50/P90 with the model evidence behind it. Cenex's independence — no downstream delivery interest — means the contingency is challenged, not inflated, so the P90 holds and savings are realised at the P75 / P60 award reset.

Which Framework Is Your Project Funded Under?

Tell us the framework — TMR, Commonwealth / DITRDCA, or a state mandate — and we'll build the probabilistic estimate and contingency it requires.