TMR Framework · 1st Edition, March 2023

TMR Project Risk Management & Contingency Development Process Manual

How Transport and Main Roads requires risk to be identified, modelled and costed on Queensland transport projects — base estimate plus probabilistically modelled contingency, expressed at P90, with a P50 reserve held by the project manager and a P75 value locked in at tender award.

What the manual is

The document that governs contingency on QTRIP projects

The TMR Project Risk Management and Contingency Development Process Manual (1st Edition, March 2023) is the document that governs how risk is identified, modelled and costed on Queensland transport infrastructure projects. It sits beneath TMR's corporate Risk Management Framework and ISO 31000:2018, and is read alongside the Project Cost Estimating Manual (PCEM), the OnQ project-management framework, Engineering Policy 153 (Risk Context Profiles, July 2020) and the Australian Government's cost-estimation guidance notes.

It applies to the pre-construction phases — planning, concept and development — of QTRIP (Queensland Transport and Roads Investment Program) projects, and treats risk and contingency as a living process re-assessed at every milestone. Its legislative basis is the Financial Accountability Act 2009 (Qld) and the Financial and Performance Management Standard 2019.

Base Estimate

The estimator's best prediction of quantities and current rates — before any inherent or contingent risk, or escalation, is added.

Contingency

A financial reserve for identified, accepted risks. Developed probabilistically and expressed at P90 beyond the business-case milestone.

Escalation

Anticipated cost increase over time (inflation, market, supply). Distinct from contingency — modelled and reported separately.

Why a client should care: if a project is QTRIP-funded, the contingency in its estimate must be developed the TMR way — base estimate plus probabilistically modelled contingency, expressed at P90, with a P50 reserve held by the project manager. An estimate that uses a flat-percentage contingency will not satisfy TMR for anything but the smallest, lowest-risk jobs.

Gating thresholds

The Project Assurance Framework (PAF) applies to capital expenditure ≥ $100M or significant risk/complexity; OnQ Type 1 gating applies to projects of $50M–<$100M. The risk process streamlines ISO 31000 into six activities: establish scope, context & criteria → identify → analyse → evaluate → treat → monitor, review, communicate & consult.

The core split

Planned (inherent) vs unplanned (contingent) risk

This is the manual's central conceptual split (Section 8). TMR's formal pairing is inherent vs contingent — not "inherent vs residual". The two kinds of risk are modelled in completely different ways.

Planned / inherent risk (§8.1)

Variability in the measured quantities and rates already in the base estimate. These are always present — you cannot remove them, only quantify them. They are modelled as ranges on existing line items.

Example: concrete priced at $200–$250/m³ over a quantity of 75–100 m³.

Modelled as: three-point ranges — lowest likely / most likely (= base estimate) / highest likely — using continuous distributions (Triangular, PERT).

Unplanned / contingent risk (§8.2)

Unmeasured items that may or may not occur — discrete risk events not in the base estimate. They are two-dimensional: each has a severity (cost impact) and a likelihood of occurring at all.

Example: a contaminated-soil discovery that may add $1.5M, but only has a 30% chance of occurring.

Modelled as: discrete events drawn from the dollarised risk register, using discrete functions (Bernoulli, Binomial, Discrete) for the probability×impact structure.

How each kind of risk is modelled

Inherent ranges vs contingent events

Inherent risk lives inside existing line items as a min/most-likely/max range. Contingent risk lives outside the base estimate as discrete events, each scaled by its probability of occurring.

INHERENT (PLANNED) RISK Range on a measured base-estimate line item LOW $200/m³ MOST LIKELY = base est. HIGH $250/m³ CONTINGENT (UNPLANNED) RISK Discrete events: probability × impact $1.5M p=0.60 Contam. soil $0.9M p=0.35 Utility move $0.4M p=0.15 Approval delay $ IMPACT
Inherent risk → continuous distributions

Modelled directly on base-estimate line items as lowest likely / most likely / highest likely ranges (Triangular, PERT). The cost is incurred either way — only its magnitude is uncertain.

Contingent risk → discrete functions

Modelled as separate two-dimensional events (Bernoulli, Binomial, Discrete) drawn from the dollarised risk register. Each may not occur at all — severity is scaled by likelihood.

Both feed the same simulation

Inherent ranges and contingent events are combined in one Monte Carlo run, with correlation modelled, to produce the S-curve from which P50, P75 and P90 are read.

Section 8.2

The ten contingent-risk categories

The manual sets out ten categories of unplanned, contingent risk to scan for at every milestone. Where given, its historical-data benchmarks are shown below as the manual's illustrations — not fixed Cenex rates.

1. Design development change

"Scope creep" as design matures and refinements emerge. Historically benchmarked at 3%–8% of construction cost per design stage.

2. Standards & policy change

Revised technical standards, government policy, planning schemes or regulatory requirements emerging during development or delivery.

3. Third-party influence

Utility and service relocations, rail interfaces, council requirements and external approvals controlled by parties outside the project.

4. Revised functionality

Scope change that alters the project's benefits — new service, performance or operational requirements as the project develops.

5. Principal's costs

Costs borne directly by the principal (PM, consultants, approvals, internal staff). Historically ~30% of the unspent portion in early stages.

6. Project delay

Schedule extension and the escalation/overheads it triggers. The manual cites Flyvbjerg (2004): projects on average delayed 20% versus the business-case date.

7. Changes during implementation

Variations and changes after award. Average cost increase ~11% of the EFCT (estimate for comparison with tenders) at award.

8. Property acquisition

Valuation uncertainty, negotiation and tribunal outcomes, easements, and business relocation/disturbance costs.

9. Unmeasured / unidentified items

Allowances for scope not yet quantified: 1–3% (S2D), 3–5% (business case), 5–7% (strategic estimate) of total construction cost.

10. Project-specific risk items

Risks unique to the individual project that do not fall under the nine generic categories — captured directly from the risk workshop.

Two related TMR instruments

Engineering Policy 153 prescribes Risk Context Profiles across 10 profiling categories (geotechnical; environment / weather / cultural heritage & native title; vulnerable road users; stakeholders; procurement; project management; safety & wellbeing; contract administration; construction; finalisation). TMR's Risk Assessment & Ratings Matrix uses 8 risk dimensions (WHS; time/schedule; assets/operations/services; performance & capability; historical & Indigenous heritage; environmental/climate; media & reputation; financial).

Section 9

Deterministic vs probabilistic contingency

The manual sets out two "distinctly different" methods — and is unambiguous about which it prefers.

Deterministic (§9.1)

A flat percentage on the base estimate (item- or factor-based). The manual states it "is not recommended by the department or projects funded by the Australian Government" and "can potentially deliver very inaccurate contingency provisions."

Acceptable only: as an approximation to P50/P90 where risk-adjusted out-turn is < $25M. Annexure A's factor-based tool rates six factors (scope, risk identification, constructability, key dates, site information, interfaces).

Illustrative only: in the manual's worked example these sum to 35% total contingency for P90, with the P50 contingency set at 40% of the P90 contingency (= 14%).

Probabilistic (§9.2) — preferred

Quantitative risk analysis using Monte Carlo simulation on a structure of base estimate + contingency (+ escalation). Inherent risks are modelled on line items; contingent risks as discrete events.

Tooling: @RISK is TMR's named/recommended tool (Crystal Ball also referenced). External estimators must supply @RISK-compatible model files.

Settings: Uniform / Triangular / PERT / Discrete distributions; rule-of-thumb 10,000 iterations (more to smooth the S-curve); correlation must be modelled, or total risk is underestimated.

Why probabilistic wins

A flat percentage vs a distribution-derived contingency

A deterministic flat percentage is a single guessed number bolted onto the base estimate. A probabilistic contingency is read off a simulated distribution that reflects the project's actual risks — defensible, and tied to a confidence level.

DETERMINISTIC Flat % — a single guessed figure BASE estimate +35%? contingency no confidence level attached PROBABILISTIC Read off a simulated distribution P50 P90 contingency = P90 − base, at 90% confidence
Mandatory probabilistic triggers

The Australian Government mandates Monte Carlo for all federally funded projects with total out-turn (P90) > $25M. TMR mandates it for high-risk/high-value work — state projects > $10M and federal projects > $25M.

Deterministic = an approximation, not an answer

It carries no confidence level and no link to the project's specific risks. The manual permits it only below the $25M out-turn threshold, as a rough stand-in for P50/P90.

Section 11 · The signature TMR mechanic

P50, P90, P75 and contingency drawdown

All three confidence levels are read off the same S-curve (the cumulative probability distribution from the Monte Carlo run). Each one is owned by a different party, and the gap between them drives the savings the program reinvests.

P50 — budget & PM reserve

The most likely estimate; 50% likelihood of not being exceeded. Used for budget-setting. The project manager holds a contingency reserve up to P50.

P90 — total out-turn

"Unlikely to be exceeded" at 90% confidence. TMR's estimating policy mandates P90 for all estimates beyond the business-case milestone. P90−P50 is held at portfolio level.

P75 — APDV at award

At tender award an Approved Project Delivery Value (APDV) is set at P75 — the EFCT run through the model. Applies to projects > $25M.

The hero mechanic

The S-curve: P50, P75 and P90 — and the savings returned to the program

The cumulative S-curve maps cost ($) against the probability of not being exceeded. The PM holds to P50; portfolio holds P90−P50; at award the APDV is set at P75. Where the tender-award P75 lands below the business-case P90, the difference is project savings returned to the program for reinvestment.

0% 50% 75% 90% 100% P50 PM reserve P75 APDV @ award P90 portfolio out-turn SAVINGS → PROGRAM P90 − P75 PROJECT COST ($) → PROBABILITY NOT EXCEEDED
P50 — project manager reserve

The PM is given a contingency reserve up to P50, the budget-setting level. Day-to-day risk drawdown is managed against this reserve.

P75 (APDV) — the revised budget at award

At tender award the EFCT is run through the Monte Carlo model and the Approved Project Delivery Value is set at P75. APDV applies to projects > $25M.

P90 − P75 = savings returned to the program

Project savings = business-case P90 budget − tender-award P75 (APDV), returned for reinvestment. Manual worked example: P90 $2,301,268 − P75 $1,995,444 = $305,824. The savings policy applies to projects ≥ $10M total budget (with exclusions such as local-government grants, corridor preservation and the natural-disaster program).

Tiered contingency ownership

Project (to P50) → portfolio (P90−P50) → consolidated via APDV at award (P75). The total project cost / "Estimated cost" = base estimate + contingency + escalation, expressed at P90 (the total out-turn cost).

The source data

The risk register and the risk workshop

The probabilistic model is only as good as the data behind it. Two instruments supply that data — both run continuously across the project life cycle.

Risk register (§7.1.2.3)

Described as "the most essential document". It captures the nature and level of each risk, the owner, mitigation measures, and likelihood and consequence — with consequence expressed in dollars.

  • Created at project start; continually updated
  • The source data for the probabilistic model
  • Every Project Proposal Report (PPR) includes a summarised risk-register table

Risk workshops (§7.3.1)

"A vital component", held at every milestone, run in three phases:

  • Before — facilitator preparation; distribute information
  • During — define what counts as a risk; complete EP153 Risk Context Profiles before assessment
  • After — consolidate; a typical agenda is given in Annexure C

Qualitative analysis (§7.4.1) — a screen, not the answer

TMR's Risk Assessment and Ratings Matrix (likelihood × consequence heatmap) is suitable only for Type 3 / low-risk projects and as the early-lifecycle screen feeding the quantitative analysis. It does not replace the Monte Carlo model for high-value or high-risk work.

Section 11 & governance

Governance, review and the federal-submission output pack

Where projects are large or federally funded, the manual prescribes both the governance route and the exact contents of the @RISK output pack that must accompany the submission.

Governance route

  • Medium-to-high-risk projects must be submitted to the Policy, Planning and Investment Division and recorded in the Portfolio Investment Register.
  • Contingency ownership is tiered: project (to P50) → portfolio (P90−P50) → consolidated via APDV at award (P75).
  • Independent peer review: Infrastructure Australia provides peer review of the project cost report where federal funding is ≥ $250M.

The federal-submission @RISK output pack (projects > $25M)

Federal submissions for projects > $25M must include the workshop details, SMEs and top risks with mitigations; the underlying risk register; and the full @RISK output set with re-runnable input files:

Required output What it demonstrates
Histogram The shape and spread of simulated cost outcomes
S-curve Cumulative distribution from which P50, P75 and P90 are read
Simulation summary Sampling type, iteration count and random-number generator (RNG)
Tornado / regression-rank table Which inputs drive the most cost variance (sensitivity)
Summary statistics At 5% intervals from 5% to 95%
Re-runnable input files So the reviewer can reproduce and stress-test the model

Reporting & control-effectiveness

Ongoing reporting (§11) covers contingency spent-to-date plus forecast versus baseline; remaining/unallocated contingency; opportunity value offsetting demand; ineffective treatments; and an overall statement on contingency health. Control-effectiveness ratings: Effective (<3% failure likelihood), Largely effective (<10%), Partially effective, and so on.

Our approach

How Cenex delivers TMR-compliant contingency

Independent, first-principles, framework-aligned. Cenex builds the contingency that satisfies the manual — and challenges it, rather than inflating it.

Probabilistic, the TMR way

First-principles base estimate; inherent risk modelled on line items; contingent risk modelled from a dollarised risk register; @RISK at 10,000 iterations with correlation modelled; S-curve reported at P50/P90 with P75 for award.

Workshops & EP153 profiles

Cenex facilitates the milestone risk workshops and produces the EP153 Risk Context Profiles, the dollarised risk register, and the federal-submission-ready @RISK output pack — histogram, S-curve, tornado, and summary stats at 5% intervals.

Independence that holds the P90

No downstream delivery interest. Contingency is challenged, not inflated — sized to genuine residual risk so the P90 holds and savings are realised at the P75 APDV, returned to the program.

Cross-framework fluency

The TMR manual rarely sits alone. Cenex aligns the same model to the Commonwealth (DITRDCA) P50/P90 out-turn requirements and the RES Contingency Guideline best-practice tests in one consistent run.

Keep reading

Related frameworks & methods

The TMR manual is one of three named frameworks Cenex builds contingency against. Explore the rest of the cost-risk hub.

RES Contingency Guideline

The cross-jurisdiction best-practice authority on contingency development (3rd Edition, 2025).

Commonwealth (DITRDCA) Cost Estimation

The federal funding gate — P50 approval basis, P90 held and released on demonstrated need.

Frameworks Compared

TMR vs RES vs Commonwealth, side by side — thresholds, P-values and contingency ownership.

Risk Modelling & Management

Cenex's QRA and Monte Carlo service — methodology, contingency, sensitivity and when you need it.

See also the related PCEM chapter, Managing Risk & Developing Contingencies, and the cost-risk hub overview.

Need TMR-compliant probabilistic contingency?

Cenex delivers independent, first-principles, @RISK-based contingency that satisfies the TMR manual at P50/P90 with P75 for award — and the federal-submission output pack to match.