DITRDCA Cost Estimation Guidance
Applies to projects seeking funding under the Infrastructure Investment Program.
- GN2: the base estimate excludes contingency and escalation, and is broken down in the Project Cost Breakdown (PCB) categories.
- GN3A (v2, Nov 2023): probabilistic P50 and P90 outturn for projects over $25M total project cost; risk factors are the preferred method; 5,000–10,000 iterations; correlation tested at 0 and 1.
- GN4 (v3, July 2026): escalation sits outside contingency; outturn is P50 and P90 by financial year.
Stage names follow the department's Notes on Administration; confirm the current names for each submission. See also our DITRDCA guide.